Measure J Construction to Begin June 2018

***Timelines Updated Wednesday, April 19, 2017***

Planning and design of Cypress College’s Measure J construction projects are currently underway. Groundbreaking for both the new SEM building and new Veterans Resource Center with renovated Student Activities Center begins next April and June, respectively.

The new SEM building is expected to open April 2020; the new VRC and renovated SAC are anticipated to open at the end of 2019.

The pond area will be impacted by construction and laydown areas during the projects. Due to noise and obstructed passageways, events should be held elsewhere during construction.

The new SEM building will be built in a portion of Lot 7 near the current SEM building. The entire lot will be closed during construction.

SEM Building Timeline

Program Validation: June-October 2016
Schematic Design: November 2016-March 2017
Design Development: March-July 2017
Construction Documentation: June-October 2017
Groundbreaking: June 2018
Construction Completion: June 2020
Furniture, Fixtures, Equipment: June-September 2020
Opening: September 2020

Veterans Resource Center and Student Activities Center Timeline

Program Validation: December 2016-February 2017
Schematic Design: February-April 2017
Design Development: April-July 2017
Construction Documentation: July-October 2017
Groundbreaking: June 2018
Construction Completion: August 2019
Furniture, Fixtures, Equipment: August-September 2019
Opening: September 2019

Veterans Memorial Plaza Timeline

TBA

Please remember all future dates are tentative and highly subject to change.