Project List
The ballot initiative was passed in fall 2014, providing NOCCCD with $574 million. The funding allocated to Cypress College = $225 million.
Measure J Funds: Cypress College Allocation
Phase 1 Projects | Funds Spent to Date | $118.8 Million |
Phase 2 Projects | Anticipated Costs | $52.9 Million |
Phase 3 Projects | Anticipated Costs | $19.5 Million |
Contingency/Escalation | $6.3 Million | |
Phase 4 Projects | Available Funds | $27.5 Million |
Total Measure J Funds | $225 Million |
Targeted to Improve
- Science
- Technology
- Engineering
- Math
- Nursing
- Technical job training facilities
- Educational resources and support services for veterans
Measure J Completed Projects – Phase 1
- IT Infrastructure Upgrades (VRC/SAC/SEM) – Completed 2021
- Mass Communications & Security System Upgrades (VRC/SAC/SEM) – Completed 2021
- New SEM Building – Completed 2021
- Baseball Clubhouse – Completed 2021
- Veterans Memorial/Pond Refurbish – Completed 2021
- New Veterans Resource Center – Completed 2021
- New Student Activities Center – Completed 2021
- Swing Space Gym II Improvement – Completed 2018
- Parking Lot 5 Realignment – Completed 2018
Active Projects – Phase 2
- Fine Arts Building Renovation – Target Completion Summer 2025
- Fine Arts Swing Space (old SEM) – Target Completion Winter 2023
- HRC Temporary Relocation – Target Completion Summer 2023
- IT Network Refresh – Target Completion Summer 2022
- Campus-Wide Security System Upgrades (Phase 1) – Target Completion Summer 2022
Future Projects – Phase 3
- Central Plant Upgrades
- L/LRC Exterior Study Garden
- Women’s Athletics Softball Field Upgrades
- Pool Restoration
- Campus-Wide Security System Upgrades (Phase 2)